• Laying of 110mm HDPE Pipes- 7200 meter and 160mm HDPE Pipes- 500 meter, including excavation, backfilling, compacting, cart away surplus materials. Providing the bedding and surrounding materials in trench, laying of detectable warning tape
  • Removal of old pipes, fittings, house connection fittings & transferring scrap to near by Client warehouse
  • House Connections till meter as per Nama standard -728 nos
  • Asphalt Road crossing and Reinstatement of Asphalt Pipes- 1315 meter
  • Reinstatement of Interlock, Tiles, Concrete.- 5820 meter
  • Re-connection to the existing Gate Valve & Air Valve- 15 nos
  • Re-connection to the existing Fire Hydrant - 36 nos