• Laying of 110mm HDPE Pipes- 3150 meter, including excavation in excavation in all types of soil, trench of suitable width including back-filling with well graded soil materials, compacting, cart away surplus excavated materials.Providing the bedding and surrounding materials in trench, laying of detectable warning tape
  • Removal of old pipes, fittings, house connection fittings & transferring scrap to near by Client warehouse
  • House Connections till meter as per Nama standard - 210 nos
  • Asphalt Road crossing and Reinstatement of Asphalt Pipes- 370 meter
  • Reinstatement of Interlock, Tiles, Concrete.- 2980 meter
  • Re-connection to the existing Gate Valve & Air Valve- 10 nos
  • Re-connection to the existing Fire Hydrant - 10 nos
  • HDD work for Newly constructed Asphalt Road - 5 nos